Shifting and Tilting of Well Foundations

Shifting and Tilting of Well Foundations

 

Shifting and tilting problems occurs generally during sinking process of well foundations. If proper care is not taken, they will cause serious problems and weaken the stability of foundations. Precautions to avoid shifting and tilting, limitations and rectifying methods are discussed below.

Shifting and Tilting of Well Foundations

  • When the well is moved away horizontally from the desired position, then it is called shifting of well foundation.
  • When the well is sloped against vertical alignment,it is called tilting of well foundation.

Precautions to Prevent Shifting and Tilting

It is safer and economical to avoid tilting and shifting of wells by adopting the following preventive measures:

  • The outer surface of the well curb and steining should be level, straight, and smooth.
  • The radius of the well curb should be kept 2-4 cm more than the outer radius of the well steining.
  • The cutting edge should be sharp and of uniform thickness.
  • The steining should be built in lifts and the entire steining height should be built in one straight line from bottom to top at right angles to the plane of the curb.
  • Dredging should be uniform on all sides of the well. For a twin well, dredging should be uniform in both the wells.
  • The well should be constructed in stages of small height increments.
  • The magnitude and direction of sinking of wells should be properly and carefully monitored on a continu­ous basis to identify any tilt or shift and adopt appropriate corrective measures immediately to rectify the same.
  • If the well shows a tendency for tilting, dredging should be done on the higher side. If this does not bring required improvement, sinking should be stopped and should be resumed only after the tilting is corrected.
  • Dredged material should not be deposited unevenly around the well.
  • When a kentledge is used to provide additional sinking effort, it should be placed evenly on the loading platform.

Limitations

  • The maximum tilt allowed in case of well foundation is 1 in 60.
  • The shift in well foundation should not be more than 1 % of depth of sunk.
  • Beyond the above limits, well foundation is considered as dangerous and in such a case, remedial measures to rectify shifting and tilting should be followed.

Rectifying Methods

Rectifying methods for Rectification of shifting and tilting problems in well foundations are as follows:

  1. Eccentric loading
  2. Excavation on higher side
  3. Water jetting
  4. Pulling the well
  5. Using hydraulic jacks
  6. Using struts
  7. Excavation under cutting edge
  8. Wood sleeper under cutting edge

1. Eccentric loading

  • The well tilt can be rectified by placing eccentric loading on the higher side. Higher side is nothing but the opposite side of tilt or lower side.
  • A loading platform is constructed on the higher side and load is placed on it.
  • This eccentric load will increase downward pressure on higher side and correct the tilt.
  • The amount of load and eccentricity is decided based on the depth of sinking.
  •  Greater is the depth of sinking of well, larger will be the eccentricity and load.
Fig 1: Eccentric Loading on Well Foundation

2. Excavation on Higher Side

  • When well is tilted to one side, excavation should be increased on the other side which is opposite to tilted side.
  • This technique is useful only in the initial stages of well sinking.
Fig 2: Excavation on Higher Side

3. Water Jetting

  • Water jetting on external surface of well on the higher side is another remedial measure for rectifying tilt.
  • When water jet is forced towards surface of well, the friction between soil and well surface gets reduced and the higher side of well becomes lowered to make well vertical.
Fig 3: Water Jetting on Higher Side

4. Pulling the Well

  • The well can be pulled towards higher side using steel ropes.
  • One or more steel ropes are wound around the well with wooden sleepers packed in between well and ropes to prevent damage to the well steining by distributing load over to larger area of steining.
  • Pull should be carefully done otherwise,shifting of well foundation may occur.
Fig 4: Pulling the Well Foundation

5. Pushing using Jacks

  • Another method to rectify tilting and shifting of well foundation is using hydraulic jacks or mechanical jacks, the tilted well can be pushed from lower side to higher side.
  • Neighbor vertical well foundations or suitable arrangements made will give support to the jack system.
  • Care should be taken while pushing the well otherwise the well may shifts.
Fig 5: Pushing using Jacks

6. Using Struts

  • By providing struts as supports on the lower side or tilted side of well, further tilting can be prevented.
  • Wooden sleepers are provided between struts and well steining to prevent damage to well steining and to distribute pressure to larger area.
  • Struts are rested on firm base having driven piles.
Fig 6: Strutting the Well From Lower Side

7. Excavation under Cutting Edge

  • This technique is used for hard strata soils. In this method, the well is de-watered first and open excavation is carried out exactly under the cutting edge on the higher side.
  • If de-watering is not possible, soil strata is loosened using suitable equipment with the help of professional divers.

8. Wood Sleeper under Cutting Edge

  • If tilting towards lower side is increasing,then wooden sleepers are placed under cutting edge on lower side to control the tilting temporarily.
  • When well is corrected to vertical level, this sleepers can be removed.
Fig 7: Wood Sleeper under Cutting Edge

13 Songs That Describe What it Means to Be a Manager

13 Songs That Describe What it Means to Be a Manager

 

Being a manager is a tough job.

You want to get the most out of your people. You want your team to hit its goals. And it would be nice to also, you know, spend some small sliver of your day not thinking about work.

But it can all be overwhelming.

Well, we here at LinkedIn Learning have hundreds of courses to help you work through some of biggest challenges all managers face. But sometimes, sometimes before you learn, you just need to know you aren’t alone

And that’s where this post comes in. Because we are 99 percent certain the songs in this article are actually all about being a manager – so know that Cher has been there, too.

1. When you post an open role on your team.

Hiring the right people is such a big part of managing. So, every time you post an open role on your team, you aren’t just looking for the good.

You are looking for the great. Dare I say, the heroic.

2. When your team is running multiple high-profile projects at once.

It’s great when your team gets to work on a high-profile project. It’s even better when your team is working on multiple high-profile projects at once – what a chance to shine!

At the same time, that comes with some pressure as well. But don’t worry; we believe in you.

And so does Freddie Mercury.

3. When your best employee leaves the team.

 

On one hand, you feel good for them, as hopefully it’s for a better opportunity.

But, on the other hand, you’ll miss them. It’s okay, take a minute and acknowledge the pain.

4. When you want to connect with an employee, but they are keeping their guard up.

You want to connect with a new employee. But maybe they aren’t quite ready to let their guard down just yet.

It’s okay, it’ll happen eventually, we promise.

5. When someone unfairly criticizes one of your employees.

Because nobody puts baby in the corner.

6. When your team comes in under-budget.

Who doesn’t love cheap thrills?

7. When your once-antagonistic team starts to gel.

Pitch Perfect – one of the few cinematic masterpieces of our time – is the epic drama about a motley crew of girls who, at first, have their own fiefdoms and don’t collaborate well. But, after going through a lot, they come together to gel as a unified team.

Sound like your team? Then this is the collaboration for you.

8. When you make a mistake managing an employee and instantly regret it.

Had a night where you couldn’t sleep because you said the wrong thing?

Well, you aren’t alone. Every manager has been there. Just crank up the Cher and know it’ll all work out.

9. When you are dealing with an employee problem you don’t know how to solve. 

All managers need help sometimes. We hope LinkedIn Learning can occasionally provide it :).

10. When an employee continues to struggle – but you still believe in them. 

Maybe they are inexperienced, maybe they have low confidence, maybe they need to learn some new skills.

But you know they have the ability to do the role – and just want them to work with you, so they can prove it to the world.

11. When your team crushes its goals.

Your goals obviously can’t hold you — and nor can the ceiling.

12. When you see your coaching pay off as one of your employees is developing nicely.

Let out those tears of pride. You’ve earned it.

13. When one of your employees says “thank you.” And means it.

 

This doesn’t happen often. But, when it does, dang does it feels good.

 

Beam Analysis Excel Spreadsheet

Beam Analysis Excel Spreadsheet

 

Shear Force, calculates flexible moment and deficit in 31 locations along the length of member “Embalal”. Members’ length can only be supported with single size or medium support, which is supported by 2, 3 or 4 lengths. The results of the analysis are produced in a tabular form and are imprinted in 3 graphs for quick understanding.
The program uses a common equation for the default equation with Shear Force, Bending Moment, and Member Time. When the middle support is specified, the solution setup is set up and the middle support response account is set up.

Spreadsheet Download

The program works internally consistent force and length unit. Permitted use of mixed units to help refine the results. The pregnancy and elastic modules of the member’s section can be defined in any unit. Similarly, any desired unit can set the reflection value. To make the unit specific, go to unit sheets and describe the ball, distance, intensity, modulus and deficit units. You need to calculate and count the conversion elements of the centralized unit from the selected unit. Sample Value This sheet is provided for your guidance. Units can not be mixed in one project file. All beams of the selected unit file apply. This means that if the units change between the formation of data files, then bees must be redefined bee characteristics in conjunction with selected bees.

Download Link

 

ICE Load Analysis on Structural Steel

ICE Load Analysis on Structural Steel

 

According to the ASCE705I ASCE 7-05 code, the Spreadsheet Program written in MS-Excel for determining ice load due to the frozen rain on structural steel members. Specifically, quality and related and necessary parameters are determined to calculate the level of snow loading of different types of structural steel members.

 

Program ideas and limitations:

1. This program specifically follows section 10.0, Ice Load – ASCE 7-5 standard, “atmospheric torque,” and “minimum design load for building and other structures”.

2. This program sets the ice load based on the ASCE 7-05 code, which determines the specific diameter for a specific size and for comparative purposes, it calculates the size of ice load based on the actual size of the size.

3. This program uses the Database and Database Properties database from AISC version 13.0 “Shape Database” CD-ROM version (12/2005), and AISC 13th Edition manual list (12/2005).

 

Download Link

Wind Load Calculator Excel Spreadsheet

Wind Load Calculator Excel Spreadsheet

 

ASCE705W ASCE 7-05 Written for analysis of air load for code and structures for Spreadsheets program written in MS-Excel. In particular, air pressure is calculated by coefficients and corresponding parameters and net design calculations or calculation of air pressure.

Wind Load Calculator

This program is a workbook with the nine (9) worksheets described below.

*Simplified – Analysis using simplified method for improving home with <= 60 ‘
*MWFRS (low-rise) – main air-power resistance system for low-end house <= 60 ‘
*MWFRS (any HT) – the main wind power protection system for any height building
*Wall C and C wall components and cladding analysis
*Roof C and C – Roof material and cladding analysis
*Stack and Tank – Condensed Chimney, Stack and Vertical Tank Analysis
*Open framework (no roof) – Analyze the open framework without ceiling
*Wind Maps – Basic Wind Speed ​​Maps (Figure 6-1 for code ASCE 7-05)
*For more information on load type, read more about load count topics.

Program ideas and limitations:

1. This program uses the “ASCE 7-02 Air Load Regulation Usage Guidelines” to determine the external air pressure group used in outdoor air pressure assistants, ‘GCP’, Wall C and C and Roof C and C worksheets. . (Note: A version of this document that was applicable to the SSC 7-05 code was not available.)

2. Workshops for “MWFRS (any HT)”, “Wall C and C”, and “Roof C and C” are applicable for home with an average ceiling height of up to 500 feet.
3. For “simplified” analysis, it is applicable to low-growth house by meeting the criteria of Section 6.4.1.

4. In the worksheet for simplified analysis, the design is calculated for each side of the MWFRS air load. MDFRS design design is considered to be loaded in total length of the building length or length.

5. Worksheet for “MWFRS (Low-Rise)” is applicable for low-rise home defined in section 6.2.
6. The “open structures” worksheet is applicable for open frames without a 500 ft tall roof. It can be used for open-process-type structure and pipe / utility racks and bridges.
5. User defined steps can be used to define air pressure distribution in the worksheet for ‘Z’, “MWFRS (any HT)”, “Wall C and C”, and “Roof C and C”.

7. “May MWFRS (no HT)”, “Stack and Tank” and “Open Structures” worksheets can handle “strict” and “flexible” buildings and structures. For “strict” buildings or structures, this program uses a counting value of 0.85 or a glass effect factor, ‘g’ code code code 6.5.8.1. For “flexible” buildings or structures, this program calculates the ‘gf’ according to the vibration section 12.8.2.1, code based on the approximate time of code 6.5.8.2, where the formula X ‘X’ = City * H ^ X 0.75 is considered to be.

8. Workshops for “Wall C and C” and “Roof C and C” for flat roof buildings, Galilei roof buildings with roof corners <= 45 degrees and ceiling corners with monosclosure roof buildings <= 3 degrees.

9. “Stack and Tank” worksheet is applicable to the 600 feet long arch welded structure.

10. This program has several “comment boxes” that contain information including input or output items, usage of equations, data tables, etc. (Note: The appearance of the “Comment Box” is indicated by the “red triangle” in the top right corner of a cell, in particular the mouse pointer to move the contents of the “comment box” to the desired room.)

 

Download Link

Mumbai to Fujairah in 2 hours! UAE plans underwater bullet train to boost connectivity with India

Mumbai to Fujairah in 2 hours! UAE plans underwater bullet train to boost connectivity with India

 

Imagine not having to undergo hours of air travel and underwhelming flight meals to reach the UAE from India. Imagine hopping on to a train and reaching the coasts of UAE in a matter of two hours. That is exactly what is being explored in a concept by UAE’s National Advisor Bureau Limited.

In this futuristic mode of transport, the bureau is looking at the possibility of connecting Mumbai to the city of Fujairah in the UAE through an underwater rail network. As mentioned in Khaleej Times, not only will this mode transport passengers, it could also be used to exchange goods and oil exports as mentioned by the bureau’s director and chief consultant Abdulla Alshehhi during the UAE-India Conclave in Abu Dhabi.

“This is a concept. We plan to connect Indian city of Mumbai with Fujairah through ultra-speed floating trains. The project aims to boost bilateral trade. There will be export of oil to India from Fujairah port and import of excess water from Narmada River, north of Mumbai. In addition, other GCC partners can also improve export and import,” Alshehhi told a gathering of businessmen and industry experts, as mentioned in the daily.

 

The total length of the rail network will be less than 2,000 km but the underwater part could pose unique challenges and a lot of aspects would need consideration. “We will do feasibility study of the project. This is concept but a cool project to look at,” he added.

The project that aims to boost bilateral trade will benefit UAE, India and others in the region, Alshehhi mentioned.

Meanwhile, India is already working on ambitious transport projects such as the bullet train and Hyperloop. Will this project see the light of day remains to be seen.

Concrete: 4 Innovations You’ve Never Heard Of

Concrete: 4 Innovations You’ve Never Heard Of

 

Concrete — a material that can trace its interactions with humans back to the Roman era more than 2,000 years ago — is the most popular material used today. When tonnage is compared, the use of concrete outweighs plastic, wood, aluminum and steel combined. What’s equally amazing about concrete is the material’s ability to continuously be the center of innovation. Here are some of the more exciting concrete innovations that are expected to change the industry.

1. Self-Healing Concrete

It’s the bane of every engineer and construction professional’s existence: concrete cracks. Once a concrete project cracks — which all will at some point — leakage can occur, disrupting the integrity of the material. Scientists at the Netherlands’ Delft University of Technology have invented bioconcrete. This is concrete that is mixed using the same techniques as traditional concrete except that it also contains specific bacteria. These bacteria generate crystals that enclose their cells. When mixed with other secretions, such as proteins and sugar, a glue-like substance is generated. When the concrete cracks, these bacteria are activated and form either limestone or calcite, a process that seals the gaps.

2. 3D Printed Concrete

3D printing is a concept that has been getting a great deal of attention within the past few years with advancements being made. Not only can it be used to print items such as plastics ad auto parts, it can now also print concrete objects. In another project originating from the Netherlands — this time from a technology-focused university called TU Eindhoven — 3D printers can now be used to make items made of concrete. Using a huge printer manufactured by a Dutch company, Rohaco, this concrete printer looks like an overhead crane that has a swivel head that pushes the concrete out in a more focused and customizable way. While implementation within the industry is still in its infancy stages, 3D printed concrete has created pavilions and recyclable concrete products.

3. Eco or Green Concrete

With its continued focus on the environment, it shouldn’t be a surprise that the construction industry is developing materials that are more ecologically friendly. Concrete typically generates a great deal of carbon. In fact, it produces so much carbon that the typical carbon footprint of concrete is nearly as large as the weight of the material itself. When mixed with fly ash — a waste material that is generated by power stations that burn coal — and other materials such as concrete and Portland cement, many benefits become evident. Not only does using fly ash reduce the carbon footprint of the concrete by as much as 25 percent, it also requires less water. This eco-friendly concrete is creamier and easier to place within projects. Finally, using the fly ash helps keeps this waste product from being dumped in landfills.

4. Pervious Concrete

Another environmentally-friendly concrete solution that is poised to gain a great deal more traction within the construction industry is pervious concrete. Traditionally, concrete has been impervious — meaning water runs off of it, allowing architects to direct its flow in more focused ways. At least, that was the original intent. This strategy, though, led to numerous incidents of urban flooding, erosion, pollution and other problems. As a result of these serious ecological issues, a solution — pervious concrete — was developed. Sometimes called a porous pavement, pervious concrete is made of larger particles than traditional concrete. This creates voids within the concrete that allow for the gradual infiltration of rainwater into the ground below.

The above-noted innovations are just a few that are being tested within the concrete industry. As a material, concrete has been evolving for more than 2,000 years. All the evidence points to a continuation of exciting changes in the future as well.

Lime & Cement Stabilisation Process

Lime & Cement Stabilisation Process

 

Introduction

Soil stabilisation, in terms of pavement construction, is the process of (usually insitu) pulverising and moisture conditioning by mixing various binders with soil, compaction and trimming as necessary. This improves soil characteristics preferred for construction in terms of moisture content, density, strength (CBR%), permeability, plasticity index and shrink swell characteristics. Most material types, clay through to crushed rock, are suitable for stabilisation. Seeking advice early during the design/feasibility stage enables planning for efficient use of stabilisation.

Stabilisation

Lime and/or cement stabilisation is often used to improve the properties of site won materials, to enable their use in a pavement and other like areas, such as dam foundations and building pad sites. Lime stabilisation of clay material reduces entrance cracking, whilst increasing the hardness of the material by up to ten times. The use of cement as a binder, after lime, can further increase the strength and durability towards that of concrete. Various binder blends, away from lime and cement, such as slag or fly ash, are commonly utilised for further benefit dependant on site conditions and requirements.

General Benefits of Soil Stabilisation

  • Saturated, wet sites can be treated to provide a working platform within a day for project continuation during wet periods/seasons.
  • Stabilisation recycles existing pavement by pulverising the existing pavement to 25mm down. Lime and or cement or other binders are then mixed with water as necessary. No imported materials and increased production rates means cost savings.
  • Strength gains often over CBR 15% or 5 times the previous strength are the result of the realignment of particles and adjustment of moisture content allowing compaction at optimum moisture content.
  • Reduce Plasticity Index (PI) in cohesive materials. For example a material with PI 20 will typically stabilise to PI < 10, say 8.

General Stabilisation for Lining Systems and Cohesive Expansion Material

  • Reduce or eliminate the need for imported clay liner by stabilising insitu materials.
  • Reduce permeability.
  • Reduce Linear Shrinkage rate up to 10%.
  • Environmental benefits of reduced geotextile, borrow pit clay and quarry import.
  • Additional environmental benefits from reducing extra excavation and disposal by modification to suitable material.
  • Improved structural stability through realignment of soil particles by ionic exchange between clay and lime.
  • Increased Strength and durability.
  • Reduced dispersion means reduced dispersion piping failure and increased erosion protection.
  • Pulverisation to 40mm down of clay, extremely weathered limestone, mudstone and siltstone provides smaller diameter conglomerates and homogenous material throughout the stabilised layer eliminating lenses, streaks, rock fissures and faults providing reduced seepage.

Lime

Note that there are many variations of lime available but only quicklime is considered suitable for lime stabilisation in the pavement construction industry and general field construction activities. Quicklime is calcium oxide (CaO) supplied commercially in a dry powder form. Agriculture Lime is a calcium carbonate (CaC03) and not suitable for pavement construction. Hydrated Lime is calcium hydroxide (Ca(OH)2) often used in the laboratory for lime saturation testing, not generally used on site for pavement construction.

Hydrated lime (calcium hydroxide), is produced by reacting water with quicklime (calcium oxide). CaO + H2O => Ca(OH)2. When calculated using the atomic weights, this converts practically to 5t Quicklime + 3t Water => 7t Hydrated lime + 1t Water Evapouration.

The pozzolanic reaction between lime with water and the silica and alumina in clay results in an ionic exchange, which permanently realigns the clay particles forming friable conglomerates. The new alignment of the particles provides less ability for the clay to absorb water around the particles. This makes the clay more waterproof, less expansive and therefore reduces the plasticity and linear shrinkage. The PI is often more than ½ and the shrinkage is often 10% of what it was. Practically this results in improved permeability less shrinkage cracking providing less chance of piping failure and seepage.

In a lime saturated environment (typically 3% to 4% quicklime), the clay-alumina and clay-silica become available to react with the free calcium to form calcium aluminates or silicates. The pozzolanic reaction is illustrated by the following equations:

Ca2+ + OH- + Available Clay Aluminium Calcium Aluminate Hydrate (CAH)
Ca2+ + OH- + Available Clay Silica Calcium Silicate Hydrate (CSH)

Stabilisation Process & Machinery

Insitu stabilisation procedures vary depending upon the type of project and the binder used. All machinery suitable for the process is purpose built for stabilisation. A range of purpose built equipment has been developed according to specific requirements of various site conditions and design specifications for the process to be effective. Adaptation of agricultural equipment and other equipment does not meet specification requirements and results in a process failure.

Preparation

Prior to stabilisation commencing it is important to ensure the surface is prepared for stabilisation ahead of stabilisation. Preparation of a surface for stabilisation includes pegging out for stringing as necessary, trimming to approximate levels and shaping to shed water and sufficient drainage to prevent water ponding where possible. Note that due to the addition of binders and density changes, some bulking may occur, however this may also be balanced by other factors such as reducing the moisture content or increasing the density of the underlying material during compaction. Immediately prior to stabilisation, the surface should be ripped to the required depth to identify and remove unsuitable material such as obstacles, organics and material too hard to stabilise.

Spreader

the Stabil-Lime Group operates a range of purpose built lime and cement spreader trucks including an articulated 4×4 all terrain spreader for particularly boggy sites. This enables the supply and distribution of a full range of binder products suitable for the insitu stabilisation process. Leading technologies are incorporated into all trucks to ensure accurate binder spread rates and containment of dust.

  • On board computers linked to load cells and farm scan distance measuring devices assist in assuring accurate spread rates.
  • All spreader trucks have sealed bulk bins to ensure the product does not start to react until it is on the ground ready to be mixed into the pavement. Spread rates (kg/m2) must vary in accordance with varying ground conditions.
  • Additional mat test can be carried out in order to confirm and adjust the spreading rate.

Water Truck

Especially during the drier months, water must be added to ensure optimum moisture content is maintained for compaction. Depending on soil conditions and moisture content water can be added before and or after spreading any binder or directly into the mixing chamber by linking the water truck to the mixer where appropriate. Not only is water vital to ensure optimum moisture content at compaction, water initiates the necessary chemical reactions with most binders.

Stabilising Machine

Prior to stabilisation commencing it is important to ensure the surface is prepared for stabilisation ahead of stabilisation. Preparation of a surface for stabilisation includes pegging out for stringing as necessary, trimming to approximate levels and shaping to shed water and sufficient drainage to prevent water ponding where possible. Note that due to the addition of binders and density changes, some bulking may occur, however this may also be balanced by other factors such reducing the moisture content or increasing the density of the underlying material during compaction. Immediately prior to stabilisation, the surface should be ripped to the required depth to identify and remove unsuitable material such as obstacles, organics and material too hard to stabilise. Rotary hoe type attachments to bob cats, tractors and the like are not accepted by the Industry for pavement construction as they are not mixing chambers, they do not ensure homogenous mixing or accurate depth control amongst other faults. Research shows pavements mixed with such machines often fail within 1-3 years because the binder and moisture have not been mixed thoroughly.

Compaction

Compaction commences after mixing. Typically stabilised materials are compacted to 95% standard, however higher compaction standards are achievable. Insitu mixing up to 400mm in a single layer requires compaction equipment large enough to achieve density throughout a layer this thick. Typically large self propelled vibratory padfoot rollers are used initially for deep compaction followed by a similar smooth drum to complete compaction of the full layer.

Final Trimming

It is normal to commence trimming the pavement before the completion of the compaction operation, ensuring good bonding of any corrected shape before is finished.

Considerations for Stabilisation

By seeking our advice early during the development stages of a project we can ensure savings are maximised by optimising the use of stabilisation in designs to reduce double handling and import and export of materials. We employ a number of qualified engineers and project managers offering sound advice based on years of experience.

In order to assess a site accurately in terms of stabilisation, ideally the following information is considered:

  • Geotechnical data including site conditions, material type and depth, sub-grade and existing pavement material.
  • Construction conditions and loading.
  • Geometric site layout proposed and existing.
  • Proposed minimum area to be treated.
  • Specification requirements typically in terms of density, CBR strength or binder content if provided.
  • Proposed award and commencement dates.

The 10 Best Conferences for Civil Engineers to Attend in 2019

The 10 Best Conferences for Civil Engineers to Attend in 2019

 

As an engineer, it is extremely important to stay current within your industry. Those who do not stay current will quickly find themselves left behind and will thus be unable to innovate on new technologies. Listed below are 10 civil engineering conferences to attend in 2019. The list is divided up into 4 categories namely; materials science engineering, water treatment engineering, new construction techniques and sustainable engineering.

Materials Science Engineering

4th International Conference on Civil Engineering and Materials Science (ICCEMS 2019)

17-19 May 2019
Bangkok, Thailand

ICCEMS 2019 will bring together the top researchers from Asian Pacific nations, North America, Europe and around the world to exchange their research results and address open issues in biomaterials, biomedical manufacturing, casting and solidification, characterisation, coatings and surface engineering, composite materials, etc. It is one of the leading international conferences for presenting novel and fundamental advances in the fields of civil engineering and materials science.”

Concrete Structures & Concrete Technology 2019

18-19 October 2018
Dallas, Texas, USA

“Concrete Structure 2019 conference will make the perfect platform for global networking as it brings together renowned speakers, researchers, business persons across the globe to a most exciting and memorable scientific event filled with much enlightening interactive sessions, world-class exhibition and poster presentations. Advances in the field of Concrete Technology are one of the crucial factors in the economic prowess of developed and developing countries. Also for the developing countries, adoption of innovative Concrete construction techniques and various versatile steel structures is paramount for the advancement of their economies.”

21st International Conference on Self-Healing Concrete in Civil Engineering

22-23 March 2019
Tokyo, Japan

“ICSHCCEA 2019: 21st International Conference on Self-Healing Concrete in Civil Engineering Applications aims to bring together leading academic scientists, researchers and research scholars to exchange and share their experiences and research results on all aspects of Self-Healing Concrete in Civil Engineering Applications. It also provides a premier interdisciplinary platform for researchers, practitioners and educators to present and discuss the most recent innovations, trends, and concerns as well as practical challenges encountered and solutions adopted in the fields of Self-Healing Concrete in Civil Engineering Applications.”

Water Treatment Engineering

New England Water Environment Association (NEWEA)

27-30 January 2019
Boston, Massachusetts, USA

“This prestigious conference, which consistently attracts over 2100 engineers, consultants, scientists, operators and students features a variety of technical sessions and over 200 exhibitor displays. The conference provides an opportunity for professional exchange of information and state-of-the-art concepts in wastewater treatment and other water environment issues. The NEWEA Annual Conference is a great forum to meet colleagues, professional allies, make new friends and exchange information.”

21st International Conference on Concrete Engineering and Technology (ICCET)

19-20 September 2019
Paris, France

“ICCET 2019: 21st International Conference on Concrete Engineering and Technology aims to bring together leading academic scientists, researchers and research scholars to exchange and share their experiences and research results on all aspects of Concrete Engineering and Technology. It also provides a premier interdisciplinary platform for researchers, practitioners and educators to present and discuss the most recent innovations, trends, and concerns as well as practical challenges encountered and solutions adopted in the fields of Concrete Engineering and Technology.”

World Water Congress & Exhibition 2019

Copenhagen, Denmark
18-23 September 2019

“Five days of critical discussions into the future of sustainable water management. Thought-leadership permeated workshops, debates, business forums, keynote speakers, technical and training sessions. Networking opportunities enabled new insights and partnerships, showcasing new ideas and solutions to solve the global water crisis.”

New Construction Techniques

3rd International Conference on 3D Printing Technologies and Innovations 

25-26 March 2019
Rome, Italy

“3D Printing Conference 2019, Rome, brings an Opportunity to attend the presentations delivered by eminent scientists, researchers, experts from all over the world and Participation in sessions on specific topics on which the conference is expected to achieve progress. It brings Global networking in transferring and exchanging Ideas. Share your excitement in promoting new ideas, developments and innovations in the field of 3D Printing Technology & Innovations.”

4th Modular Construction and prefabrication ANZ

27 February – 1 March 2019
Sydney, Australia

“The 4th edition of the conference will focus on international & well known Australian OSM & DfMA exemplars, the industry’s best practices and new innovative techniques & technologies that will strengthen and enhance the uptake of modular construction methodology in the ANZ construction industry.”

Sustainable Engineering

2nd RILEM Spring Convention & International Conference on Sustainable Materials, Systems and Structures

18-22 March 2019
Rovinj, Croatia

“SMSS2019 conference is organised as a supporting event of RILEM Spring Convention. The scope of the conference is to gather scientists, practitioners, members of technical committees and users of technical recommendations, to jointly at the same place discuss and envision the future sustainable development of materials, systems and structures in a holistic, global way.”

73rd RILEM Annual Week & International Conference on Innovative materials for Sustainable Civil Engineering (IMSCE)

25-30 August 2019
Nanjing, China

“The RILEM Annual Week & International Conference on Innovative materials for Sustainable Civil Engineering will discuss the topics such as- Fresh concrete and chemical admixtures, Hydration and microstructure characterization, Sustainable cementitious materials, Deformation and crack controlling, Durability and service life prediction, and more.”

error: Content is protected !!
Exit mobile version